Campus Development
April 22, 2019
April 22, 2019
- All construction works in phase I are completed and opened to service
March 29, 2019
March 29, 2019
Anticipated opening date for the new learning center - April 22, 2019
- Construction work progress: 98%
- Interior works progress: 85%
- Utility works progress: 99%
February 15, 2019
February 15, 2019
- Multi-purpose area is now open to the Secondary students during the pollution season
- Electricity, AC, elevator is now completed
- Construction work progress: 95%
- Interior works Progress: 62%
- Covered walkway work progress: 15%
January 11, 2019
January 11, 2019
- Construction Progress: 90% --- Expect to be ready to get the building permission by the end of January.
- VRF Air Conditioning System: Completed
- Elevator: Completed
- Interior Works progress: 25%
November 23, 2018
November 23, 2018
- Construction progress: 90%
- Tempered Glass windows & Doors: 95%
- Painting: 90%
- Ceiling: 100%
- Roof: 95%
October 29, 2018
October 29, 2018
- Construction Progress: 87%
- Tempered Glass windows & Doors: 90%
- Painting: 70%
- Ceiling: 70%
- Roof: 90%
October 10, 2018
October 10, 2018
- Overall Work progress: 80%
- Aluminum window frame: 90%
- Metal frame for blinder and windows: 100%
- VRF AC wiring installation: 80%
- Electrical, internet, and speaker cables: 90%
- Painting: 60%
September 14, 2018
September 14, 2018
- Overall Work progress: 75%
- Aluminum window frame: 50%
- Concrete and brick: 100%
- Bathroom tile: 100%
- Metal frame for blinder and windows: 100%
- VRF AC wiring installation: 50%
- Electrical, internet, and speaker cables: 90%
- Painting: 10%
August 24, 2018
August 24, 2018
- Work progress 72%
- Concrete and brick work is 90% completed
- Bathroom tiling is completed
- Metal frame for blinder and windows is now completed
- VRF AC wiring and pipe is now 80% completed
- Electrical cables progress 80%
August 10, 2018
August 10, 2018
- Work progress 72%
- Concrete and brick work is nearly completed
- Bathroom tiling was started
- Metal frame for blinder and windows is now completed
- VRF AC wiring and pipe is now 70% completed
- Electrical cables progress 60%
July 24, 2018
July 24, 2018
- Work progress 65%
- Roof tiles installation 75%
- Electrical work 50%
- Brick work 60%
May 20, 2018
May 20, 2018
- Work progress 33%
- Concrete pouring for the roof structure beams is scheduled to do on May 26, 2018
- Installation of the roof structure is going to start around the end of May
April 27, 2018
April 27, 2018
- Concrete pouring for the floor beams of the 2nd floor is scheduled to do on April 28-29, 2018
- 26 out of 28 posts were completed
- The area beside the covered court will be kept as the materials storage for the construction of Library and Cafeteria Building until the end of the summer break
April 24, 2018
April 24, 2018
- Ground floor pavement is completed
- 26 out of 28 posts was poured and ready to do the ceiling beam for the ground floor
Secondary School Building
Secondary School Building
- The Secondary School Building is now completed
CMIS Campus Development Project
CMIS Campus Development Project
Living & Learning Campus with a Strong Sense of Identity
Contractor: Thepburapha Yothakarn Co.,Ltd.
Architecture and Engineering: ASANA Architect Co.,Ltd.
Consultant: ASANA Architect Co.,Ltd.
Anticipated Completion: